It takes 10 workers 24 hours to do a job.
Fill in the chart.

It takes 10 workers 24 hours to do a job Fill in the chart class=

Respuesta :

biggersis1968p8xgn0 biggersis1968p8xgn0
  • 02-06-2018
5 in 48 
10 in 24
20 in16
30 in12
40 in 8
50 in 4
Answer Link

Otras preguntas

Which of the following consists of the policies, procedures, and resources required to ensure that a business can continue to function after a major catastrophe
PLEASEEEE HELPPPPPPPPPPP
How is energy associated with food stored? a. potential energy in chemical form b. kinetic energy in chemical form c. potential energy in mechanical form d. kin
what are three names for little words akeelah and the bee
How did the Comanche resist the terms of the Medicine Lodge Creek Treaty? A. by relying on government rations and raiding B. by refusing to send their child
Chinese porcelain was highly valued in Europe for its beauty, style, and durability. However, imported porcelain from China was very expensive. Crafters in Germ
Is the Yarra river a young river, mature river, or an old river?
two Hundred eighty-one thousand in standard form
Somebody PLEASE HELP!!! Giving brainliest to the best answer. What process controls water loss by the plant, so that the plant will not wither up and die? A. R
Which audience may stop your message from getting to its intended audience?