If a project will take 35 employees 2940 hours to complete how many hours will each employee have to work

Respuesta :

afrazi01p8qv5j
afrazi01p8qv5j afrazi01p8qv5j
  • 02-07-2018
To find out how many hours each employee will need to work, we divide 2940 hours by 35 to evenly split the hours among each of the workers.
2940 / 35 = 84
This means that each employee will need to put 84 hours of work into the project to complete it.

Answer Link

Otras preguntas

Grains are are rich in which nutrient? a. carbohydrates b. fats c. proteins d. vitamins
The length of a rectangular parking lot at the airport is 2/3 mile. If the area is 1/2 square mile, what is the width of the parking lot?
What is the continuous amperage rating for the diamond gzv4000 power supply?
Why is it important for the signers of the declaration of independence to justify their political break with great britain?
What Martin Luther King intends to say in this sentence: "In the End, we will remember not the words of our enemies, but the silence of our friends."
Nancy wants to put a birdseed mix in her birdfeeder. The mix is 20% wild bird seed and 80% sunflower seed. Her birdfeeder can hold 8 cups of birdseed. How much
(7x-3) = (12x-7) solve for x
If I have added new headings in my document and wanted to update my table of contents, what would I need to do to ensure the new headings are included in the ta
How can individual rights and the common good come into conflict?
What was the system by which branded cattle were allowed to graze freely on unfenced property?