Comparing a static planning budget to actual costs is not a good way to assess whether variable costs are under control. T/F

Respuesta :

Nyctalus
Nyctalus Nyctalus
  • 11-09-2019

Answer: False

Explanation: Static budget refers to that budget which is made for the upcoming period. A static budget incorporates anticipated values of inputs and outputs in it. It does sometimes assumes extreme business environment conditions.

Therefore, it is not feasible to compare the actual budget with the static plan as there is a high chance that both will differ by a high amount.

Hence, the given statement is false.

Answer Link

Otras preguntas

What are some behavioral adaptations for a porcupines?
the area of Alicia's garden is 81 square feet. what are the dimensions of her garden?
WHAT is the answers to 2a 2b and 2c ?
What is the simplified answer to the problem 9+5r-9r??
How do you solve a system of equations by elimination when the signs are the same
The first land battle of the civil war took place near ________, Virginia, on july _ _, 18_ _At this battle, the union army ___________ the confederate army.wha
Ho does differentiation change an embryo as it develops
70-q-q-2q=80 We'll this is confusing
The first land battle of the civil war took place near ________, Virginia, on july _ _, 18_ _At this battle, the union army ___________ the confederate army.wha
solve for x:    x to the negative 3rd power is equal to 27 over 64