When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

Normal rainfall is slightly acidic, which means its ph must be
Which battle was the turning point in the pacific theater of wwii?
Which of these is a good guideline to follow when designing a presentation slide show? Use dark backgrounds Avoid large type Avoid fancy fonts Use only one
Use a special right triangle to write tan 60º as a simplified fraction.
1. Crystals of ammonium chloride, NH4Cl, seem to disappear when mixed with water. The resulting clear liquid containing ammonium chloride and water is a A) co
What are 5 characteristics of a Utopian society?
The atoms of blue paper _____ blue light. absorb reflect transmit
Italian cities lost many of their cultural aspects and traditions because they were __________ Roman culture. A. opposed to B. ignorant of C. threatened by D
What is the distance between (3, 5.25) and (3, –8.75)?
What were the achievements of king saul