Jin schedules 496 hours for a project. He plans to work 8 hours each day. How many days will it take to complete the project?​

Respuesta :

penguinlife90 penguinlife90
  • 01-12-2021

Answer:

62 days

Step-by-step explanation:

496/8 = 62

Answer Link
clickykeyboardasmr
clickykeyboardasmr clickykeyboardasmr
  • 01-12-2021

496/8=62

Hope this helps!

Answer Link

Otras preguntas

Which action would most likely cause the equal employment opportunity commission to intervene
can someone help me solve the perimeter of this shape??
A line has slope 2/3 and y–intercept −2. Which answer is the equation of the line? y=2/3x+2 y=2/3x−2 y=−2x+2/3 y=2x+2/3
​a corporation has all the rights and responsibilities of _____.
22. Ian deposits $440.00 into his bank account. Ian uses Auto payer to deduct 1/4 of his deposit to pay monthly bills. Which number represents the amount by whi
What are the types of chemicals that must have a material safety data sheet?
In 1999, ruth dreifuss became switzerland's first woman president and also its first _______ president.
Fusion: A.requires high temperatures B.occurs in the sun and other stars C.creates less radioactive waste than fission D.all of the above
Derek wrote the equation s= 0.1t to show how much he was saving each month. The variable s equals the amount Derek saves and t equals derek’s total income. Whic
What did everyone in America think they ought to have a chance to be after WWII?