if 10 man can work 6hours.How many more men are needed towork in 4 hours​

Respuesta :

mathstudent55
mathstudent55 mathstudent55
  • 03-12-2021

Answer:

5 more men

Step-by-step explanation:

10 men do a job in 6 hours.

To do the job in 2 hours, 1/3 of the time, you need 3 times as many men.

30 men do a job in 2 hours.

To do the job in twice the time, 4 hours, you need half the men.

15 men do a job in 4 hours.

15 men - 10 men = 5 men

You need 5 more men.

Answer Link

Otras preguntas

Humans and animals have critical periods. True or False?​
Im writing a conclusion for an essay i need help if anyone can help? I just wanna know what i should add or improve on ? This is for AP english Looking Through
PLZZ help me with this good explanation with the zero product property and factoring PLZZ read carefully ❤️❤️
. Suppose client A initiates an FTP session with server S. At about the same time, client B also initiates an FTP session with server S. Provide possible source
What is 123 as a percent????
I need help pleaseee​
What is the rate of change for the function represented in the table? $0.50 per book $0.67 per book $1.07 per book $1.50 per book
The bombing the church where 4 girls were killed happened in 1963, the movie takes place in 1964- 1965. Why do you think the scene of the bombing was included i
Which simple machine is best used to split apart an object A. A screw B. A lever C. A wedge D. A pulley
what monetary policy would the federal reserve adopt to control inflation