Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

The house and senate can only pass amendments of the constitution if
Why aren’t lung transplants very common?
The clause in article i, section 8, that grants power to do whatever is necessary to execute specifically delegated powers is called the
Evaluate for this problem Help!!!
Choose the conditional statement that can be used with its converse to form the following biconditional statement: "An angle is a right angle if and only if it
Jonathan completed 60% of his passes as the football team quarterback. If he completed 90 passes, how many passes did he throw in all?
Young adults (those under 18) are protected by the law, even when they brake the law. in most states, people under the age of 18 can be charged with breaking th
the united states entered world war i because
BRAINLIEST!!! The surface area of a triangular pyramid is 80 m2. If the pyramid is enlarged by a scale factor of 2, what is the surface area of the scaled image
please help me please